Question 7

Question 1

When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.

a.children

b.antecedent

c.successor

descendant

Question 2

  • A ____ path includes all tasks that are vital to the project schedule.

a. Critical

b. Baseline

c. Vital

d. Foundation

Question 3

  • Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.

a. Critical

b. Foundational

c. Vital

d. Baseline