Question 1
- ____ is open-source software that is supported by a large group of users and developers.
a. Both b and c
b. Microsoft project standard
c. Microsoft project Professional
d. Open workbench
5
Question 2
- A _____ cannot be started until one or more other tasks are completed.
a. Dependent task
b. Concurrent task
c. Predecessor task
d. all of the above
Question 3
- A ____ is an event that could affect a project negatively.
a. Risk
b. Menace
c. Threat
d. Doubt