Question 1
A ____ might involve maximums for one or more resources.
a. Task group
b. Constraint
c. Bottom-up Technique
d. Successor task
Question 2
When several tasks can start at the same time, each is called a(n) ____ task.
a.asynchronous
b.concurrent
c.baseline
d.synchronous
Question 3
Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task.
a.ancestor
b.a priori
c.predecessor
d.antecedent